After a failover occurs, which two actions must be performed on Switch-B to manually preempt the operational primary role back to Switch-A?

Posted by: Pdfprep Category: 300-615 Tags: , ,

Refer to the exhibit.

After a failover occurs, which two actions must be performed on Switch-B to manually preempt the operational primary role back to Switch-A? (Choose two.)

A. Configure the local vPC role priority to have a lower value than Switch-A.

B. Configure the local vPC role priority to have a higher value than Switch-A.

C. Disable and then re-enable the vPC peer-keepalive link.

D. Configure the local vPC role priority to have the same value as Switch-A.

E. Disable and then re-enable the vPC peer link.

Answer: BE