What happens?

Posted by: Pdfprep Category: E20-555 Tags: , ,

Three jobs are running, all with a priority of 5. A new job with a priority of 6 needs to be run.

What happens?
A . The job engine pauses a priority 5 job and runs the new job until completion, then restarts the paused job from the point at which it was interrupted.
B . The job engine runs the new job in parallel with the other jobs.
C . The job engine pauses a priority 5 job and runs the new job until completion, then restarts the paused job from the beginning.
D . The job engine queues the new job until one of the currently running jobs completes.

Answer: D

Leave a Reply

Your email address will not be published.