An existing IBM San Volume Controller DH8 cluster consists of two I/O groups with DH8 nodes running IBM Spectrum Virtualize 7.6. Performance analysis the cluster requires significant additional memory for the I/O workload.

What is the first step the technical specialist should recommend?
A . Expand the cluster to 4 I/O groups using HD8 nodes
B . Add additional memory to the existing DH8 node
C . Replace the existing cluster DH8 nodes with SV1 nodes
D . Upgrade the cluster to the recommended level of code

Answer: C