When will the next backup run, if all prior backups completed successfully?

Posted by: Pdfprep Category: VCS-278 Tags: , ,

Refer to the exhibit.

A backup policy uses a Full backup schedule with a schedule type of Frequency: 1 day. The start window for the schedule is configured as shown in the exhibit:

The administrator runs a manual backup at 10:00 on Thursday.

When will the next backup run, if all prior backups completed successfully?
A . Friday at 2:00
B . Friday at 10:00
C . Monday at 2:00
D . Monday at 1:00

Answer: C