Which attribute on the story was automatically updated by this action?

Posted by: Pdfprep Category: C2010-825 Tags: , ,

The scrum master moves a story in the Quick Planner from the backlog to a sprint plan.

Which attribute on the story was automatically updated by this action?
A . Release
B . Owned by
C . Planned for
D . Filed Against

Answer: D