Which constraint was documented by the architect?

Posted by: Pdfprep Category: 3V0-42.20 Tags: , ,

An architect is helping an organization with the Conceptual Design of an NSX-T Data Center solution.

This information was gathered by the architect during the Discover Task of the Enagagement Lifecycle:

– There are applications which use IPv6 addressing.

– Network administrators are not familiar with NSX-T Data Center solutions.

– Hosts can only be configured with two physical NICs.

– There is an existing management cluster to deploy the NSX-T components.

– Dynamic routing should be configured between the physical and virtual network.

– There is a storage array available to deploy NSX-T components.

Which constraint was documented by the architect? (Choose the best answer.)
A . Dynamic routing should be configured between the physical and virtual network.
B . There are applications which use IPv6 addressing.
C . Hosts can only be configured with two physical NICs.
D . There are enough CPU and memory resources in the existing management cluster.

Answer: A

Leave a Reply