Which day would you expect a RECOVER DATABASE following that day’s backup to take the longest time to complete?

Posted by: Pdfprep Category: C2090-600 Tags: , ,

A production database has the following daily midnight backup schedule which includes all table spaces. The database incurs the same volume of daily activity (inserts, updates, and deletes).

Sunday C Delta

Monday C Incremental

Tuesday C Delta

Wednesday C Delta

Thursday C Incremental

Friday C Delta

Saturday C Full

Which day would you expect a RECOVER DATABASE following that day’s backup to take the longest time to complete?
A . Friday
B . Monday
C . Saturday
D . Wednesday

Answer: D