Which four actions should you perform in sequence?

Posted by: Pdfprep Category: MB-320 Tags: , ,

DRAG DROP

A pharmaceutical manufacturer uses Process manufacturing.

You are consolidating planned batch orders for a specific medication. The order must cover two weeks of demand. No other items need to be consolidated. You need to change the coverage group of the items.

Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.

Answer: