Which indicators must you activate in the phase type in customizing?

Posted by: Pdfprep Category: C_S4PPM_1909 Tags: , ,

You want to control the execution of subsequence phases in project management.

Which indicators must you activate in the phase type in customizing? NOTE: There are 2 correct answers to this question
A . The Release Success phase only after Approval indicator
B . The approval phase indicator
C . The completion required indicator
D . The complete phase when Granting Approval indicator

Answer: A,B