Which is a key component of the Frame the Programme or Project process?

Posted by: Pdfprep Category: MOVF Tags: , ,

Which is a key component of the Frame the Programme or Project process?
A . Initial briefing meeting
B . Team selection
C . Resource analysis
D . Idea selection

Answer: A