Which of ONE of the following additional defect report fields would be MOST beneficial for the sprint team to add?

Posted by: Pdfprep Category: CTFL-2018 Tags: , ,

Your agile project has scheduled a final sprint before release to fix and re-test all open defects with a priority level of 3 or above.

The following defect report shows the defect fields that are currently being captured on the system.

Title: Unable to add excursions to pre-paid cruises

Date raised: 21/05/18

Author: Emma Rigby

Status: Fixed

What occurred: I went to book an excursion for a pre-paid cruise but received an error message saying, ‘Facility not available’. I can book excursions on cruises that have not yet been fully paid.

What should have occurred: Requirement 3.12 says clearly that customers can add excursions after cruises have been fully paid so the facility should have been available (when an additional amount may now need to be paid).

Priority: 2

Software build: 2.1

Test level: System test

Environment details: System test 3

Which of ONE of the following additional defect report fields would be MOST beneficial for the sprint team to add?
A . Severity.
B . Test Script Id.
C . Actual results.
D . Expected results.

Answer: A