Which of the following is the correct order in the risk management phase?

Posted by: Pdfprep Category: 312-38 Tags: , ,

Management decides to implement a risk management system to reduce and maintain the organization’s risk at an acceptable level.

Which of the following is the correct order in the risk management phase?
A . Risk Identification, Risk Assessment, Risk Treatment, Risk Monitoring & Review
B . Risk Treatment, Risk Monitoring & Review, Risk Identification, Risk Assessment
C . Risk Assessment, Risk Treatment, Risk Monitoring & Review, Risk Identification
D . Risk Identification. Risk Assessment. Risk Monitoring & Review, Risk Treatment

Answer: A