Which of the following parameters should you consider when calculating there order point for a material? There are 3 correct answers to this question.

Posted by: Pdfprep Category: C_TS452_1909 Tags: , ,

Which of the following parameters should you consider when calculating there order point for a material? There are 3 correct answers to this question.
A . Lot-sizing procedure
B . Expected daily requirements
C . Safety stock
D . Replenishment lead time
E . Checking group for availability check

Answer: B,C,D