Which of the following risks represents the highest level of risk to the project?

Posted by: Pdfprep Category: CTFL_Syll2018 Tags: , ,

Which of the following risks represents the highest level of risk to the project?
A . Likelihood of failure = 1%, potential cost of impact = $1m.
B . Likelihood of failure = 10%, potential cost of impact = $500,000.
C . Likelihood of failure = 20%, potential cost of impact = $150,000.
D . Likelihood of failure = 5%, potential cost of impact = $500,000.

Answer: B

Leave a Reply

Your email address will not be published.