Posted by: Pdfprep Category: OG0-093 Tags: OG0-093 exam questions, OG0-093 practice exam, The Open Group Certification Post Date: October 26, 2020 Pdfprep2020-10-26T07:06:11+00:00 Which phase of the ADM is used to finalize a set of transition architectures that will support implementation?A . Phase DB . Phase EC . Phase FD . Phase GE . Phase H View Answer Answer: C Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.
Leave a Reply