Which three steps should you verify in the production test flow?

Posted by: Pdfprep Category: MB-300 Tags: , ,

You are upgrading a Dynamics 365 Finance solution.

You must run functional test passes for the upgraded solution.

You need to plan a production environment test flow for the solution.

Which three steps should you verify in the production test flow? Each correct step presents part of the solution. NOTE: Each correct selection is worth one point.
A . Purchase orders are generated
B . Item requirements are present
C . Production order processing occurs
D . Production orders are generated
E . The item master is designed and released to a legal entity

Answer: ABD