How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?

Posted by: Pdfprep Category: PSM II Tags: , ,

How much time is allowed between the conclusion of the current Sprint and the start of the next Sprint?
A . Maximum of one day for Sprints that are time-boxed to two weeks.
B . None. A new Sprint starts immediately following the conclusion of the previous Sprint.
C . Enough time for the last Increment to finish testing.
D . Enough time for the Product Owner to prepare the Product Backlog for Sprint Planning.
E . All of the above are allowed.

Answer: B