The Development Team can cancel the Sprint:

Posted by: Pdfprep Category: PSM II Tags: , ,

The Development Team can cancel the Sprint:
A . When the availability of the Product Owner is less than expected.
B . When the requirements for the work to be done become unclear or not understood.
C . It can’t. Only Product Owners can cancel Sprints.
D . When the Sprint Backlog is determined to be unachievable.
E . When too many impediments occur.

Answer: C