The team decides a story is too big to do in one iteration. The correct technique to apply at this point is:

Posted by: Pdfprep Category: IIBA-AAC Tags: , ,

The team decides a story is too big to do in one iteration. The correct technique to apply at this point is:
A . MoSCoW approach
B . Story decomposition
C . Epic analysis
D . Story partitioning

Answer: B

Explanation:

Reference: https://www.excella.com/insights/make-your-agile-user-stories-manageable-through-story­decomposition