You change an active project baseline and save it. Then, the system creates a new baseline.

What are the statuses of the previous baseline and new baseline?
A . Previous baseline: "active with pending changes" New baseline: "in planning"
B . Previous baseline: "obsolete" New baseline: "in planning"
C . Previous baseline: "obsolete" New baseline: "active"
D . Previous baseline: "active with pending changes" New baseline: "in approval"

Answer: D