Which cost rates does the system consider when it valuates internal project time recordings? Note: There are 2 correct answers to this question.

Posted by: Pdfprep Category: C_BYD01_1811 Tags: , ,

Which cost rates does the system consider when it valuates internal project time recordings? Note: There are 2 correct answers to this question.
A . Labor resource cost rate
B . Project-specific cost rate
C . Service cost rate
D . Employee cost rate

Answer: A,C