Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)

Posted by: Pdfprep Category: C_TSCM42_67 Tags: , ,

Which activities lead to a reduction of the capacity requirements for an operation? (Choose three)
A . Rescheduling the operation
B . Posting the goods receipt for the production order
C . Confirming the operation
D . Setting the status technically complete (TECO)
E . Reducing the order quantity

Answer: C,D,E