A risk management program would be expected to:

Posted by: Pdfprep Category: CISM Tags: , ,

A risk management program would be expected to:
A . remove all inherent risk.
B . maintain residual risk at an acceptable level.
C . implement preventive controls for every threat.
D . reduce control risk to zero.

Answer: B

Explanation:

The object of risk management is to ensure that all residual risk is maintained at a level acceptable to the business; it is not intended to remove every identified risk or implement controls for every threat since this may not be cost-effective. Control risk, i.e., that a control may not be effective, is a component of the program but is unlikely to be reduced to zero.