What is the avoided cost in his proposal?

Posted by: Pdfprep Category: CBAF-001 Tags: , ,

An IT department needs to upgrade its hardware to run the new version of an established operating system. The cost of this required upgrade is $2 million. As an alternative, the IT director has suggested that the company should change to a completely different operating system. Although this will cost $6 million, the change will bring many other benefits, including cheaper maintenance costs and increased security.

What is the avoided cost in his proposal?
A . $2 million.
B . $4 million.
C . $6 million.
D . $8 million.

Answer: A