Which of the following would BEST be managed with the "keep satisfied" stakeholder management strategy?

Posted by: Pdfprep Category: CBAF-001 Tags: , ,

Which of the following would BEST be managed with the "keep satisfied" stakeholder management strategy?
A . Those with high power/influence and no interest in the project.
B . Those with high power/influence and some interest in the project.
C . Those with some power/influence and high interest in the project.
D . Those with some power/influence and some interest in the project.

Answer: B