Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose all that apply.)

Posted by: Pdfprep Category: PSM I Tags: , ,

Which are NOT appropriate topics for discussion in a Sprint Retrospective? (Choose all that apply.)
A . Definition of “Done”.
B . How the team does its work.
C . Team relations.
D . The value of work currently represented in the Product Backlog.
E . Arranging the Sprint Backlog for the next Sprint.

Answer: AE