Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?

Posted by: Pdfprep Category: PSM I Tags: , ,

Which statement best describes the Sprint Backlog as outcome of the Sprint Planning?
A . It is a complete list of all work to be done in a Sprint.
B . Every item has a designated owner.
C . Each task is estimated in hours.
D . It is the Development Team’s plan for the Sprint.
E . It is ordered by the Product Owner.

Answer: A