Which three of the following are time-boxed events in Scrum? (Choose three.)

Posted by: Pdfprep Category: PSM I Tags: , ,

Which three of the following are time-boxed events in Scrum? (Choose three.)
A . Release Testing.
B . Release Retrospective.
C . Sprint Retrospective.
D . Sprint Planning.
E . Sprint Testing.
F . Sprint 0.
G . Daily Scrum.

Answer: CDG