You are working with the Solution Documentation function within the SAP Solution Manager System.

Which is the correct sequence to create your own process? Please choose the correct answer.
A . Solution Business Processes Scenario Process Interface or Process Step
B . Solution Interface or Process Step Business Processes Scenario Process
C . Solution Process Business Processes Scenario Interface or Process Step
D . Solution Scenario Business Processes Process Interface or Process Step

Answer: A