Which of the following content in addition to the SAP EariyWatch Alert (EWA) report can be included in the Service Level Report after the mandatory and managed system configuration has been successfully completed?

Posted by: Pdfprep Category: C_SM100_7208 Tags: , ,

You are using the SAP Solutions Manager Service Level Report (SLR) session configuration tool.

Which of the following content in addition to the SAP EariyWatch Alert (EWA) report can be included in the Service Level Report after the mandatory and managed system configuration has been successfully completed? Note: There are 2 correct answers to this question.
A . Standard queries (RCA)
B . System and application monitoring (MAI)
C . Business process monitoring
D . System configuration

Answer: B,C