Which of the following is MOST closely associated with a business continuity program?
A . Confirming that detailed technical recovery plans exist
B . Periodically testing network redundancy
C . Updating the hot site equipment configuration every quarter
D . Developing recovery time objectives (RTOs) for critical functions
Answer: D
Explanation:
Technical recovery plans, network redundancy and equipment needs are all associated with infrastructure disaster recovery. Only recovery time objectives (RTOs) directly relate to business continuity.