A member of the Development Team takes the Scrum Master aside to express his concerns about data security issues.
What should the Scrum Master do?
A . Add security to the definition of “Done”.
B . Tell the Product Owner to stop further development of features until the issues are fixed.
C . Create a Product Backlog item for security.
D . Go check with the testers.
E . Ask the person to share the issue with the team as soon as possible.
Answer: E