Posted by: Pdfprep Category: PMI-200 Tags: PMI-200 exam questions, PMI-200 practice exam, PMI-ACP Certification Post Date: October 17, 2020 Pdfprep2020-10-17T22:29:34+00:00 Which term best describes an Agile project’s approach to risk analysis?A . RegressionB . ParetoC . QualitativeD . Monte Carlo View Answer Answer: D Prev QuestionNext Question Author Pdfprep Leave a Reply Cancel replyYour email address will not be published. Required fields are marked *Comment * Name * Email * Website Save my name, email, and website in this browser for the next time I comment.