Which of the following activities do not occur at the end of the Sprint?

Posted by: Pdfprep Category: CSM-001 Tags: , ,

Which of the following activities do not occur at the end of the Sprint?
A .  Software development
B .  Release deployment
C .  Sprint review meeting
D .  Quality assurance testing

Answer: A,D