You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?

Posted by: Pdfprep Category: CSM-001 Tags: , ,

You are the Scrum Master. The Sprint will complete in two days. Each day of the Sprint is equivalent to 8 hours. The team has just enough time to complete all tasks in the remaining 16 hours with the exception of three tasks. Of these three tasks, two tasks (a total of 6 hours) are required to complete one Product Backlog item and one task (an estimate of 2 hours) is required to complete another Product Backlog item. How should the development team handle the remaining three tasks?
A .  The development team should negotiate with the Product Owner on the definition of "done".
B .  The development team should work the extra 8 hours to complete their commitment to the Product Owner
C .  The development team should place the two Product Backlog items back onto the Product Backlog
D .  The development team should keep the three tasks on the Sprint Backlog for the next Sprint and completethose tasks first

Answer: A