Which of the following is the GREATEST advantage to using this approach?

Posted by: Pdfprep Category: CISA Tags: , ,

Based on the guidance of internal audit, an IT steering committee is considering the use of a balanced scorecard to evaluate its project management process.

Which of the following is the GREATEST advantage to using this approach?
A . Project schedule and budget management will improve.
B . Performance is measured from different perspectives.
C . Information is provided in a consistent and timely manner.
D . Project will be prioritized based on value.

Answer: B