Which of the following would be the MOST appropriate action for the project manager with respect to the change request?

Posted by: Pdfprep Category: CISA Tags: , ,

An IS auditor is involved with a project and finds an IT project stakeholder wants to make a change that could affect both the project scope and schedule.

Which of the following would be the MOST appropriate action for the project manager with respect to the change request?
A . Recommend to the project sponsor whether to approve the change
B . Modify the project plan as a result of the change
C . Evaluate the impact of the change
D . Ignore out-of-scope requests

Answer: C

Leave a Reply

Your email address will not be published.