During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project’s scope.

Posted by: Pdfprep Category: CCBA Tags: , ,

During a requirements elicitation workshop, a stakeholder raises an issue that is outside of the project’s scope.

The business analyst (BA) facilitating the workshop should:
A . note the issue in the Issue Register to be considered by the Project Manager.
B . ignore the stakeholder’s comment and proceed with the agenda.
C . consider the issue’s impact on the project and gain agreement with stakeholders on the next step.
D . request the stakeholder to explain the issue further so that possible solutions can be discussed.

Answer: C