A project to replace a financial system uses a waterfall methodology. Initially, meetings with the project subject matter experts (SMEs) were positive. As the project progressed through the requirements and design phases, the SMEs attended fewer meetings, resulting in a delay to the project build phase.

What should the business analyst (BA) have done to prevent the delay?
A . Selected a different project methodology
B . Requested new SMEs participate in the project
C . Modified the governance structure
D . Engaged in consistent collaboration

Answer: A