Which of the following would the BA classify as a project risk?

Posted by: Pdfprep Category: CCBA Tags: , ,

A business analyst (BA) is assessing risks on a project addressing the implementation of a new web portal.

Which of the following would the BA classify as a project risk?
A . Customer service ratings will increase with the new system
B . Current infrastructure may not support increased performance
C . Expenditures are currently below budgeted estimates
D . Support calls will increase if the change is not performed

Answer: B