What should the BA review before the meeting?

Posted by: Pdfprep Category: CCBA Tags: , ,

The business analyst (BA) is assigned a small project, requiring minor enhancements to an existing system. The BA will meet with the business sponsor and developer next week to gather information about the change.

What should the BA review before the meeting?
A . Minutes from the last steering committee meeting
B . Organizational structure of the impacted department
C . Functional design specification of the existing system
D . Current list of funded initiatives for the current year

Answer: A

Leave a Reply

Your email address will not be published.