How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?

Posted by: Pdfprep Category: PMI-PBA Tags: , ,

The business analyst receives multiple changes from different stakeholders during the requirements gathering phase of a project.

How should the business analyst track the requirements throughout the lifecycle of the project to secure the delivery of the expected solution?
A . Establish a risk traceabllity matrix and designate someone to manage each risk with the appropriate response.
B . Plan regular meetings with stakeholders to review the requirements baseline update and to discuss changes.
C . Perform inspections through the lifecycle of the project to detect any gaps and adjust the requirements baseline.
D . Record all the requirements in a matrix, review it regularly, and get approval from stakeholders.

Answer: A

Leave a Reply

Your email address will not be published.