Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?

Posted by: Pdfprep Category: PMI-PBA Tags: , ,

A business analyst is assigned to the lead analyst role for a project. This project is one of the largest in the history of the company and includes several components and complex interfaces. The system in development will be used by a wide variety of stakeholders.

Which tool should the business analyst use to trace the large number of requirements that will be generated by this project?
A . Process model
B . Configuration management system
C . Sequence diagram
D . Data dictionary

Answer: B