During validation of a project solution, the business analyst discovers that a requirement has been altered. Instead of placing the company logo in the upper-left corner of the window, it is displayed in the upper-right corner. When the business analyst asks the developer about the change, the developer says that one of the stakeholders asked directly for the change.

Which corrective action should the business analyst take?
A . Discuss the change in the next stakeholder meeting.
B . Ask the developer to correct the logo as stated in the requirement.
C . Confront the stakeholder that requested the change.
D . Follow the change control process as defined in the business analysis plan.

Answer: D