In which reference matenal can the business analyst find information about the missing project stakeholders?

Posted by: Pdfprep Category: PMI-PBA Tags: , ,

Company A has initialed a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder. is excluded from the list of stakeholders.

In which reference matenal can the business analyst find information about the missing project stakeholders?
A . Business case
B . Business analysis plan
C . Organizational chart
D . Business analyst communication plan

Answer: B