If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?

Posted by: Pdfprep Category: PRF Tags: , ,

If a project’s benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
A .  Senior User
B .  Executive
C .  Corporate/programme management
D .  Senior Supplier

Answer: C