Which statement about the Directing a Project process is FALSE?

Posted by: Pdfprep Category: PRF Tags: , ,

Which statement about the Directing a Project process is FALSE?
A .  Supports the PRINCE2 principle of manage by exception
B .  Is triggered by a request to initiate a project
C .  Covers the day-to-day activities of the Project Manager
D .  Provides a mechanism for the Project Board to assure that there is continued business justification

Answer: C

Leave a Reply

Your email address will not be published.