For which of the following risk management capability maturity levels do the statement given below is true? "Real-time monitoring of risk events and control exceptions exists, as does automation of policy management"

Posted by: Pdfprep Category: CRISC Tags: , ,

For which of the following risk management capability maturity levels do the statement given below is true? "Real-time monitoring of risk events and control exceptions exists, as does automation of policy management"
A . Level 3
B . Level 0
C . Level 5
D . Level 2

Answer: C

Explanation:

An enterprise’s risk management capability maturity level is 5 when real-time monitoring of risk events and control exceptions exists, as does automation of policy management.

Incorrect Answers:

A, D: In these levels real-time monitoring of risk events is not done.

B: In level 0 of risk management capability maturity model, enterprise does not recognize the importance of considering the risk management or the business impact from IT risk.