Which of the following should be the HIGHEST priority when developing a risk response?

Posted by: Pdfprep Category: CRISC Tags: , ,

Which of the following should be the HIGHEST priority when developing a risk response?
A . The risk response is accounted for in the budget.
B . The risk response aligns with the organization’s risk appetite.
C . The risk response is based on a cost-benefit analysis.
D . The risk response addresses the risk with a holistic view.

Answer: C