Which of the following techniques would be used during a risk assessment to demonstrate to stakeholders that all known alternatives were evaluated?

Posted by: Pdfprep Category: CRISC Tags: , ,

Which of the following techniques would be used during a risk assessment to demonstrate to stakeholders that all known alternatives were evaluated?
A . Control chart
B . Trend analysis
C . Sensitivity analysis
D . Decision tree

Answer: A